Below is the 2022 Street Resurfacing Map and List. This project entails 8.3 miles of paving with an overall budget of $1.7 Million. The project will be completed no later than the spring of 2023. Bids for the project will be accepted starting Monday, June 27 on the city’s bid express page
Downtown Newark still has many overhead electric and communication lines. These lines pose a significant health and safety hazard through the risk of fire, shock, or arc to area residents and businesses. Therefore, the City, in cooperation with AEP, has contracted with Claypool Electric to bury the lines underground in a manner consistent with current safety and building codes. The work will start downtown on November 1st and will last 6-8 months.
Construction Begins: June 13, 2022
Duration: Approximately 4 Months
Construction Administrator: ODOT
Bid Amount: $1.45 Million
Funding: ODOT, City of Newark
Thornwood Crossing Potential Construction Impacts
Thornwood Crossing Bridge Project
Construction Begins: 2023
Duration: 18 Months
Construction Administrator: ODOT
Estimated Cost: $13 Million
Funding: ODOT, City of Newark
Cherry Valley Road Bridge/Thornwood Crossing Public Involvement Meeting Information
The following are links to all documents that were presented at the Public Information Meeting held of June 22, 2016:
This project will replace the 3-span, steel beam bridge, originally constructed in 1958.
Thornwood Crossing Bridge Project
Construction Begins: 2023
Duration: 9 Months
Construction Administrator: ODOT
Estimated Cost: $3.7 Million
Funding: ODOT, City of Newark
Construction Begins: 2021
Duration: 12 Months
Construction Administrator: City of Newark (City Crews installing)
Estimated Cost: $0.3 Million
Funding: ODOT
The project location is West Church Street between North 29th Street and Dietrich Street. The project is an extension of the previous project completed west of North 29th Street, and will provide:
Construction Begins: 2024
Duration: 6 Months
Construction Administrator: ODOT
Estimated Cost: $2 Million
Funding: ODOT, City of Newark
Construction Begins: 2023
Duration: 6 Months
Construction Administrator: ODOT
Estimated Costs: $1 Million
Funding: ODOT
Construction Begins: 2024
Duration: 6 Months
Construction Administrator: ODOT
Estimated Cost: $1 Million
Funding: ODOT, City of Newark
Construction begins: 2026
Duration: 18 Months
Construction Administrator: ODOT
Estimated Cost: $6 Million
Funding: ODOT, City of Newark
Check out the Division of Water and Wastewater construction projects.